# House Construction Cost Planning: Ukunda, Kenya

> Ukunda house cost planning using the World Bank ICP 2021 national construction price-level index of 64.9, plus a GeoNames-based local comparable-search shortlist.

- Canonical: https://harth.build/resources/construction-costs/house-construction-cost-ukunda-ke/
- Last updated: 2026-09-15
- Data source: National screening observation from the [World Bank ICP 2021 API](https://api.worldbank.org/v2/sources/90/country/KEN/classification/PX.WL/series/1501200/time/YR2021/data?format=json) and [ICP data documentation](https://www.worldbank.org/en/programs/icp/data); locality and population from the [GeoNames KE dump](https://download.geonames.org/export/dump/KE.zip) (CC BY 4.0 snapshot 2026-08-26, GeoNames ID 178792). The PLI is not a city cost/m² rate, current escalation series or tender estimate.

## Key facts

| Fact | Value |
| --- | --- |
| National construction PLI | 64.9 (World Bank ICP 2021; World = 100) |
| Screening ratio to world | 0.649 (dimensionless PLI ÷ 100; not a city location factor) |
| Locality reference | -4.2929, 39.5640 (GeoNames ID 178792) |
| Snapshot population | 77,686 (36 of 50 listed Kenya places) |
| Nearest listed peer | Matuga · 14 km (great-circle distance between GeoNames reference points) |
| Estimate currency | KES (obtain a current local rate and named base date) |

## Direct answer

For early house construction cost planning in Ukunda, the World Bank ICP reports a 2021 Kenya construction price-level index of 64.9, with the world equal to 100. This is a national comparison—not a Ukunda KES/m² rate or tender estimate—so replace it with current local evidence before budgeting or procurement. The observation covers construction across Kenya in 2021; it does not measure a Ukunda market basket or current house tenders. GeoNames 178792 records the locality at -4.2929, 39.5640, with snapshot population 77,686. That ranks Ukunda 36 of 50 listed places, while Matuga is the nearest listed peer at about 14 km. Use these facts only to plan the comparable search. Obtain current local rates on a consistent area basis, then reconcile scope, taxes, fees, contingency and escalation. Retain the source, base date and reviewer when local evidence replaces the screening ratio.

*Content and cited inputs reviewed by [Scott Barrington](https://nz.linkedin.com/in/barrington), Harth founder and architectural technology specialist · Published 2026-08-26 · Updated 2026-09-15.*

## What does the 64.9 construction index mean?

The World Bank ICP 2021 construction PLI for **Kenya is 64.9**, compared with a world benchmark of 100. It is a national spatial price comparison assembled for the 2021 reference year. It does not say that house work in Ukunda costs 0.649 times a current world rate.

## Which Ukunda inputs are known?

The reproducible locality point is **-4.2929, 39.5640** (GeoNames 178792). Its snapshot population is **77,686**, ranked 36 of 50 listed places; GeoNames classifies it as a populated place in administrative area 28. These facts shape the local comparable search, not the price.

## What must a project estimate add?

For a Ukunda house project, reconcile dwelling size, structural system, envelope specification, kitchens and bathrooms. Use a consistent gross-floor-area basis and record the following before reliance.

| Estimate field | Screening record | Project requirement |
| --- | --- | --- |
| National context | ICP 2021 PLI 64.9 | Retain only as dated cross-country context |
| Local KES/m² rate | Not supplied | Current comparable with named source and base date |
| Area and scope | Gross floor area; scope unresolved | Measurement standard, specification and procurement route |
| Additions | Not supplied | Taxes, fees, site work, contingency and escalation |
| Review | Automated source and arithmetic QA | Qualified local cost review |

## Ukunda comparable-location search screen

This shortlist is computed from the checked GeoNames snapshot. Distance and population help prioritize where to request comparables; neither is used as a cost multiplier.

| Listed place | Great-circle km from Ukunda | Snapshot population | Admin area |
| --- | ---: | ---: | --- |
| Matuga | 14 | 194,252 | 28 |
| Mombasa | 29 | 1,208,333 | 37 |
| Jomvu | 34 | 163,415 | 37 |
| Mtwapa | 44 | 90,677 | 23 |
| Kilifi | 80 | 74,270 | 23 |
| Kiserian | 451 | 76,903 | 19 |
| Isiolo | 562 | 78,650 | 18 |
| Nyeri | 520 | 80,081 | 44 |

## Price-level normalization worksheet

For a validated reference rate **R** from a country with construction PLI **P**, the transparent screening calculation is **R × (64.9 ÷ P)**. At P = 100 the dimensionless ratio is 0.649; no world cost rate is asserted. Keep the reference rate's currency, base date, area basis and scope attached.

| Input | Recorded value | Release condition |
| --- | --- | --- |
| Target national PLI | 64.9 (World = 100, 2021) | Screening context only |
| Reference construction PLI P | User-supplied from the same ICP classification/year | Must match reference rate country |
| Validated reference rate R | User-supplied | Named source, currency, date, area and scope |
| Local Ukunda adjustment | Not asserted | Replace with current local comparable evidence |
| Result status | Screening normalization | Not a budget, quote or tender estimate |

## Where can you explore related guidance?

- [Explore all construction costs guidance](https://harth.build/resources/construction-costs.md)
- [Office Construction Cost Planning: Ukunda, Kenya](https://harth.build/resources/construction-costs/office-construction-cost-ukunda-ke.md)
- [School Construction Cost Planning: Ukunda, Kenya](https://harth.build/resources/construction-costs/school-construction-cost-ukunda-ke.md)
- [Retail Construction Cost Planning: Ukunda, Kenya](https://harth.build/resources/construction-costs/retail-construction-cost-ukunda-ke.md)
- [House Construction Cost Planning: Matuga, Kenya](https://harth.build/resources/construction-costs/house-construction-cost-matuga-ke.md)
- [All construction costs guidance for Kenya](https://harth.build/resources/construction-costs/kenya.md)
- [Climate Design Data: Ukunda, Kenya](https://harth.build/resources/climate-data/climate-design-data-ukunda-ke.md)
- [Daylight & Orientation: Ukunda, Kenya](https://harth.build/resources/solar-data/daylight-orientation-ukunda-ke.md)
- [Solar Altitude & Azimuth: Ukunda, Kenya](https://harth.build/resources/solar-data/solar-altitude-azimuth-ukunda-ke.md)
- [Solar Shading Design: Ukunda, Kenya](https://harth.build/resources/solar-data/solar-shading-design-ukunda-ke.md)

## Sources and method

National screening observation from the [World Bank ICP 2021 API](https://api.worldbank.org/v2/sources/90/country/KEN/classification/PX.WL/series/1501200/time/YR2021/data?format=json) and [ICP data documentation](https://www.worldbank.org/en/programs/icp/data); locality and population from the [GeoNames KE dump](https://download.geonames.org/export/dump/KE.zip) (CC BY 4.0 snapshot 2026-08-26, GeoNames ID 178792). The PLI is not a city cost/m² rate, current escalation series or tender estimate.

### Source links

- [api.worldbank.org](https://api.worldbank.org/v2/sources/90/country/KEN/classification/PX.WL/series/1501200/time/YR2021/data?format=json)

- [worldbank.org](https://www.worldbank.org/en/programs/icp/data)

- [download.geonames.org](https://download.geonames.org/export/dump/KE.zip)

## Frequently asked questions

### Does the 64.9 index give a house cost per m² for Ukunda?

No. 64.9 is the World Bank ICP 2021 national construction price-level index for Kenya, with the world equal to 100. It is a cross-country screening statistic, not a Ukunda KES/m² rate, escalation index, quote or tender estimate.

### How should a Ukunda house estimate replace this screening benchmark?

Collect current Ukunda comparables on a consistent gross-floor-area basis, reconcile dwelling size, structural system, envelope specification, kitchens and bathrooms, and state base date, currency, taxes, fees, site work, contingency and escalation. A qualified local cost professional should review the resulting project estimate.

---

- Continue in Harth (open this topic in the Harth agent): https://app.harth.build/agent?context=%2Fresources%2Fconstruction-costs%2Fhouse-construction-cost-ukunda-ke%2F
- View this page in a browser: https://harth.build/resources/construction-costs/house-construction-cost-ukunda-ke/
- All resources for agents: https://harth.build/llms.txt