Construction Costs

Office Construction Cost Planning: Abeokuta, Nigeria

Abeokuta office cost planning using the World Bank ICP 2021 national construction price-level index of 72.8, plus a GeoNames-based local comparable-search shortlist.

On this page

Last updated September 15, 2026 · National screening observation from the [World Bank ICP 2021 API](https://api.worldbank.org/v2/sources/90/country/NGA/classification/PX.WL/series/1501200/time/YR2021/data?format=json) and [ICP data documentation](https://www.worldbank.org/en/programs/icp/data); locality and population from the [GeoNames NG dump](https://download.geonames.org/export/dump/NG.zip) (CC BY 4.0 snapshot 2026-08-26, GeoNames ID 2352947). The PLI is not a city cost/m² rate, current escalation series or tender estimate.

Direct answer

For early office construction cost planning in Abeokuta, the World Bank ICP reports a 2021 Nigeria construction price-level index of 72.8, with the world equal to 100. This is a national comparison—not a Abeokuta NGN/m² rate or tender estimate—so replace it with current local evidence before budgeting or procurement. The observation covers construction across Nigeria in 2021; it does not measure a Abeokuta market basket or current office tenders. GeoNames 2352947 records the locality at 7.1557, 3.3451, with snapshot population 735,000. That ranks Abeokuta 18 of 50 listed places, while Agege is the nearest listed peer at about 60 km. Use these facts only to plan the comparable search. Obtain current local rates on a consistent area basis, then reconcile scope, taxes, fees, contingency and escalation. Retain the source, base date and reviewer when local evidence replaces the screening ratio.

Content and cited inputs reviewed by Scott Barrington, Harth founder and architectural technology specialist · Published 2026-08-26 · Updated 2026-09-15.

What does the 72.8 construction index mean?

The World Bank ICP 2021 construction PLI for Nigeria is 72.8, compared with a world benchmark of 100. It is a national spatial price comparison assembled for the 2021 reference year. It does not say that office work in Abeokuta costs 0.728 times a current world rate.

Which Abeokuta inputs are known?

The reproducible locality point is 7.1557, 3.3451 (GeoNames 2352947). Its snapshot population is 735,000, ranked 18 of 50 listed places; GeoNames classifies it as a first-order administrative seat in administrative area 16. These facts shape the local comparable search, not the price.

What must a project estimate add?

For a Abeokuta office project, reconcile workplace fit-out grade, services density, floorplate efficiency and vertical transport. Use a consistent gross-floor-area basis and record the following before reliance.

Estimate fieldScreening recordProject requirement
National contextICP 2021 PLI 72.8Retain only as dated cross-country context
Local NGN/m² rateNot suppliedCurrent comparable with named source and base date
Area and scopeGross floor area; scope unresolvedMeasurement standard, specification and procurement route
AdditionsNot suppliedTaxes, fees, site work, contingency and escalation
ReviewAutomated source and arithmetic QAQualified local cost review

Abeokuta comparable-location search screen

This shortlist is computed from the checked GeoNames snapshot. Distance and population help prioritize where to request comparables; neither is used as a cost multiplier.

Listed placeGreat-circle km from AbeokutaSnapshot populationAdmin area
Agege60683,60005
Akowonjo61308,90005
Alimosho61308,29005
Ikeja62313,19605
Ebute Ikorodu64535,61905
Oyo101736,07232
Akure204730,00048
Bauchi796693,70046

Price-level normalization worksheet

For a validated reference rate R from a country with construction PLI P, the transparent screening calculation is R × (72.8 ÷ P). At P = 100 the dimensionless ratio is 0.728; no world cost rate is asserted. Keep the reference rate's currency, base date, area basis and scope attached.

InputRecorded valueRelease condition
Target national PLI72.8 (World = 100, 2021)Screening context only
Reference construction PLI PUser-supplied from the same ICP classification/yearMust match reference rate country
Validated reference rate RUser-suppliedNamed source, currency, date, area and scope
Local Abeokuta adjustmentNot assertedReplace with current local comparable evidence
Result statusScreening normalizationNot a budget, quote or tender estimate

Sources and method

National screening observation from the World Bank ICP 2021 API and ICP data documentation; locality and population from the GeoNames NG dump (CC BY 4.0 snapshot 2026-08-26, GeoNames ID 2352947). The PLI is not a city cost/m² rate, current escalation series or tender estimate.

Frequently asked questions

Does the 72.8 index give a office cost per m² for Abeokuta?

No. 72.8 is the World Bank ICP 2021 national construction price-level index for Nigeria, with the world equal to 100. It is a cross-country screening statistic, not a Abeokuta NGN/m² rate, escalation index, quote or tender estimate.

How should a Abeokuta office estimate replace this screening benchmark?

Collect current Abeokuta comparables on a consistent gross-floor-area basis, reconcile workplace fit-out grade, services density, floorplate efficiency and vertical transport, and state base date, currency, taxes, fees, site work, contingency and escalation. A qualified local cost professional should review the resulting project estimate.